Wednesday, May 2, 2007

THE COWIES CREEK INDUSTRIAL PARK
PORTAL FRAME CONSTRUCTION








IMAGE 1: Drain cutting through side pannel
IMAGE 2: Knee joint - note where the gutter fits in
IMAGE 3: Apex - note how the two rafters are connected and where the bracing is attached
IMAGE 4: Gutter and down pipe
IMAGE 5: Roof to wall connections
IMAGE 6: Look at where gutter sits between wall and roof elements
BREAKWATER METALAND BUILDING
PORTAL FRAME:
This was a warehouse and office complex constructed using a steel portal frame.
IMAGE 1: shows the set up of the warehouse space
IMAGE 2: look at knee joints
IMAGE 3: look at ceiling construction



LYONS CONSTRCUTION COMPANY SITE IN GEELONG:

This site is currently constructing warehouses where the concrete cladding is actually a structural support.
IMAGE 1: Column to footing connection
IMAGE 2: Roof to concrete pannel connection
IMAGE 3: Slab
IMAGE 4: Look at bracing
IMAGE 5: Pannel to Pannel connection and Pannel to Rafter connection
IMAGE 6: Columns were a structural requirment throughout the space, therefore this type of construction would not be suitable if a large open span is required.
IMAGE 7: Overall roof and wall construction
IMAGE 6: Ceiling, gutter and wall connections
IMAGE 7: Apex and surroundings










Saturday, April 21, 2007

Week 2: Portal Frame Section 1



Week 3: Portal Frame Section 2



Week 4: Warehouse Section



Week 5: Wall Detail


Monday, April 9, 2007

MAJOR ASSIGNMENT RESEARCH

TALK WITH ENGINEER TOM EVANS AT EARTH TECH GEELONG OFFICE:
Discussed the Scenario of a 40m x 40m warehouse with Tom Evans. He talked about a number of design considerations and suitable structural members for a warehouse of this size constructed with a steel portal frame:
- Think about height/clearance requirements
- Roof material effects the pitch
- Limit the span of columns to around 8 - 9 metres
- Use lapt ‘z’ purlins with a depth of 250mm as they will be most efficient
- Use rod bracing
- If you use the same spacing on all walls then the same girts can be used all over
- Approopriate columns would be around 610UB
- Use broad piers of 1200mm diameter which go about 3m into the ground
- Reinforce the concrete slab with 8N28 bars space evenly around perimeter
- Use pin connections, with bolts going about 1m into the footing
- Rafters around 530UB
- Safety mesh is attached from below using a lift for safety
- Welding: CRW (Continuouse Fillet Weld) is used to fill corners on 90 degrees in a triangle section.
FSBW (Full Strength Butt Weld) is used on flanges
-HE ALSO PROVIDED PHOTOCOPIES OF INFORMATION ON PORTAL STRUCTURES

Wednesday, March 7, 2007

THE CAROUSEL, GEELONG WATERFRONT


CLOSE UP VIEW OF ROOF


DETAILED VIEW OF STEEL CONSTRUCTED ROOF CONNECTION